News Flash

Mossy Oaks Stormwater Project Updates

Posted on: December 30, 2020

Mossy Oaks update through Jan. 8

Dec. 30, 2020

Ladies and Gentlemen:

Please see the two attachments that detail work in the following two weeks in Basins 1 and 2

Basin 1 (vicinity of Duck Pond)

This week has been a very light one for the project given the Christmas break, but cleanup work has taken place throughout the area. A footbridge is being built at the west end of the Duck Pond. The coffer dam in this basin is being prepared for removal and repositioning to Basin 2. All drainage continues to function exactly as designed.               

Next week, the footbridge will be completely installed. Battery Creek Road will continue to be improved, and the final elements of ditch and drainage work will be done on Jane Way. 

The coffer dam in the vicinity of Rodgers will be removed and installed in Basin 2. The removal of the dam will take about four days; reinstallation in Basin 2 in the vicinity of Riverside Drive will take approximately a week. When the coffer dam is removed from Basin 1, the Spanish Moss Trail will be prepared for laying concrete. 

Once the concrete is installed and the entire trail inspected, the Spanish Moss Trail will be reopened for bike and pedestrian traffic. 


Basin 1 through Jan. 8

Basin 2 (vicinity of Southside Park)

The contractor will work on finishing items in the Broad Street neighborhood area in the first couple of weeks of January. The coffer dam being removed in Basin I will be relocated and installed in the vicinity of Riverside Drive. This will allow workers to install three massive headwalls, three 60-inch drainage pipes with tidal flap gates attached. After that, a concrete wall cap will be installed, and the Spanish Moss Trail will be repaved and returned to its original condition.

Basin 2 through Jan. 8

Safety!

We’ve had another great week of safety. Please continue to be careful when transiting the area. Remember, if you cannot see the heavy equipment operator, then the operator can’t see you. Please avoid this area if possible until all construction has been completed, and many thanks to our law enforcement partners for helping us maintain safety.

Stay informed

I’ve had the pleasure of speaking with many residents regarding this project. I remain available anytime to address comments, concerns, or questions, so please do not hesitate to call, email or text so that the project may address your issues as rapidly as possible. Please encourage all those affected or interested in the Mossy Oaks Project to register with the “Notify Me” application found on the City of Beaufort website (https://www.cityofbeaufort.org/list.aspx) and subscribe to the Mossy Oaks Stormwater Project updates.     

Wishing each of you a fantastic New Year!  

Cheers,

Neal Pugliese, Col USMC (Ret)
Chairman
Mossy Oaks Multijurisdictional Drainage Task Force
npugliese@cityofbeaufort.org

Facebook Twitter Email

Other News in Mossy Oaks Stormwater Project Updates

Mossy Oaks update through March 26

Posted on: March 19, 2021

Mossy Oaks update through March 5

Posted on: February 26, 2021

Mossy Oaks update through Feb. 28

Posted on: February 19, 2021

Mossy Oaks update through Feb. 19

Posted on: February 12, 2021

Mossy Oaks update through Feb. 12

Posted on: February 5, 2021

Mossy Oaks update through Feb. 5

Posted on: January 29, 2021

Mossy Oaks update through Jan. 29

Posted on: January 22, 2021

Mossy Oaks update through Jan. 22

Posted on: January 14, 2021

Mossy Oaks update through Jan. 13

Posted on: January 8, 2021

Mossy Oaks update through Jan. 4

Posted on: December 23, 2020

Mossy Oaks update through Dec. 25

Posted on: December 17, 2020

Mossy Oaks update through Dec. 18

Posted on: December 11, 2020

Mossy Oaks update through Dec. 11

Posted on: December 4, 2020

Water service interruption on Dec. 8

Posted on: December 4, 2020

Mossy Oaks update through Dec. 4

Posted on: November 25, 2020

Mossy Oaks update through Nov. 27

Posted on: November 19, 2020

Mossy Oaks update through Nov. 13

Posted on: November 6, 2020

Mossy Oaks update through Nov. 6

Posted on: October 30, 2020

Mossy Oaks update through Oct. 30

Posted on: October 23, 2020

Mossy Oaks update Oct. 13-23

Posted on: October 14, 2020

Mossy Oaks update Oct. 6-16

Posted on: October 9, 2020

Mossy Oaks update Sept. 29-Oct. 9

Posted on: October 2, 2020

Mossy Oaks update Sept. 22-Oct. 2

Posted on: September 25, 2020

Mossy Oaks update Sept. 15-25

Posted on: September 17, 2020

Mossy Oaks updates: July 21-31

Posted on: July 22, 2020