January 2016

 

Tentative Boundary Street construction schedule, subject to change:

 

Complete Right-of-Way Acquisition Fall 2015
Re-Advertise for Construction Bids May 18,  2015
Proposals / Bids Due July 11, 2015
Award of Construction Contract August 2015
Construction Start January 2016
Demolition  January through February 2016
Rough Grading March 2016
Duck Bank for Utilities February 2016 through February 2017
Drainage February 2016 through December 2016
Paving (In Sections) December 2016 through December 2017
Signals July 2016 through December 2016
Signals/Marketing October 2017 through December 2017
Landscaping August 2017 through November  2017
Substantial Construction Completion (Estimate)  Early 2018